Focus on Customers
Shamco is dedicated to understanding the needs of our customers and efficiently meeting those needs. We strive to be results orientated, dependable and professional.
Queens Park Oval
Description: To be able to handle the increased load and improve reliability for the up-coming Cricket World Cup, the 12 KV system at Queens Park Oval was upgraded. The installation consist of 1200M of 12 KV Cabling and installation of 4 Transformer Banks
Work Done: All acceptance and pre-commissioning tests.